Wednesday 12 September 2012

Electric, plumbing and bricks begin

We went down to the block again on the 9th September to have a look at the progress. At first I was a bit like :( Oh boo the bricks aren't up (as we drove up the road)

After pulling up in the driveway it became apparent LOTS of things had happened this week that I was clueless about. The electrical rough out had been completed including the heating unit in the roof, data cables, etc. The plumbing rough out also had been completed both for recycled and normal water piping. We have a real front door - YAY! and completed roof. 
We have had both shower bases put in and have a tub - woohoo! (Love the shape and depth of it too). All of hte pink batt insulation is completed inside as well and ready for plaster to be hung.The front bricks have gone up, plaster has been delivered and bricks have been piled around the house ready to go.

So... heaps has been done! See the construction tab for more photos.. hopefully bricks next week :)